Machining request MR-26-0409
ClosedCable guide block rev A, 20 pieces, operations 10 to 30. Bids due 18 Sep 2026, 15:00.
- Quantity
- 20 pieces
- 3 operations, machining only
- Due at the shop’s dock
- 9 Oct 2026
- Metal arrives 1 Oct
- Bids due
- 18 Sep 2026
- 15:00
- Sent
- 18 Sep 2026
- By Alex (demo)
Bids compared
Machining only, cheapest first, against the rules check price for the same work.
| Shop | Machining | Days | Against check | Capacity | Record | Action |
|---|---|---|---|---|---|---|
| Shop NS-014Dartmouth, NSBest | $328.00$98.00 setup, $11.50 a piece | 6 daysReady 1 Oct | 43% | 68% booked120 h a week | 96% on timeControlled Goods registered |
Rules check price for the same work: $770.27.
The request as sent
What each shop got: the operations, the drawing and model, and the email.
Operations
| Op | Operation | Specification | Machine |
|---|---|---|---|
| 10 | Mill the block, two setups | ISO 2768-m | 3-axis |
| 20 | Drill 3 × Ø12 and 2 × Ø5.5 | Per drawing | 3-axis |
| 30 | Deburr | Before anodize | Bench |
Drawing and model
The shops download them from the request in their portal.
cable-guide-block-rev-a.step
288 KB, STEP model, rev A
DB-0870-A.pdf
141 KB, drawing, rev A
Email to the shops
Sent 18 Sep 2026, 11:00 to 1 shop
Machining-only request MR-26-0409: Cable guide block, 20 pieces
Your price for operations 10, 20, 30 only. Metal arrives cut to size with its mill certificate on 1 Oct 2026. Parts due at your dock on 9 Oct 2026. Reply by 18 Sep 2026.
Closed: the quote expired on 2 Oct 2026 without an order.