Machining request MR-26-0417
AwardedSensor bracket rev B, 25 pieces, operations 10 to 40. Bids due 6 Oct 2026, 15:00.
Awarded to Shop NS-014
- Quantity
- 25 pieces
- 4 operations, machining only
- Due at the shop’s dock
- 29 Oct 2026
- Metal arrives 22 Oct
- Bids due
- 6 Oct 2026
- 15:00
- Sent
- 6 Oct 2026
- By Alex (demo)
Bids compared
Machining only, cheapest first, against the rules check price for the same work.
| Shop | Machining | Days | Against check | Capacity | Record | Action |
|---|---|---|---|---|---|---|
| Shop NS-014Dartmouth, NSAwarded | $1,150.00$400.00 setup, $30.00 a piece | 5 daysReady 18 Oct | 36% | 68% booked120 h a week | 96% on timeControlled Goods registered | WO-26-0417 |
| Shop NS-021Truro, NSNot selected | $1,310.00$460.00 setup, $34.00 a piece | 7 daysReady 20 Oct | 41% | 45% booked80 h a week | 92% on timeNot registered for Controlled Goods |
Rules check price for the same work: $3,231.58.
Shop NS-014: Program, soft-jaw fixture and first article to report included. Three setups; both bores bored and plug-gauged.
Shop ON-007 declined: Our 5-axis cells are booked this month; 3-axis work is better placed with a 3-axis shop.
The request as sent
What each shop got: the operations, the drawing and model, and the email.
Operations
| Op | Operation | Specification | Machine |
|---|---|---|---|
| 10 | Mill the base, flange and relief pocket, 3-axis, three setups | ISO 2768-m | 3-axis |
| 20 | Bore 2 × Ø30 H7, base and flange | 30.000 to 30.021 mm | 3-axis |
| 30 | Drill 4 × Ø4.5 in the base; drill and tap 4 × M4 × 0.7 in the flange | M4 through the 10 mm flange | 3-axis |
| 40 | Deburr, first article to report | FAI | Inspection |
Drawing and model
The shops download them from the request in their portal.
sensor-bracket-rev-b.step
458 KB, STEP model, rev B
DB-1042-B.pdf
413 KB, drawing, rev B
Email to the shops
Sent 6 Oct 2026, 10:00 to 3 shops
Machining-only request MR-26-0417: Sensor bracket, 25 pieces
Your price for operations 10, 20, 30, 40 only. Metal arrives cut to size with its mill certificate on 22 Oct 2026. Parts due at your dock on 29 Oct 2026. Reply by 6 Oct 2026.
Machining only. Metal arrives cut to size with its mill certificate; we book every freight leg.