Machining request MR-26-0426
AwardedActuator housing rev C, 12 pieces, operations 40 to 60. Bids due 15 Oct 2026, 15:00.
Awarded to Shop ON-007
- Quantity
- 12 pieces
- 3 operations, machining only
- Due at the shop’s dock
- 20 Nov 2026
- Metal arrives 16 Nov
- Bids due
- 15 Oct 2026
- 15:00
- Sent
- 14 Oct 2026
- By Alex (demo)
Bids compared
Machining only, cheapest first. A split job’s share has no check price of its own.
| Shop | Machining | Days | Capacity | Record | Action |
|---|---|---|---|---|---|
| Shop ON-007Cambridge, ONAwarded | $1,009.00$265.00 setup, $62.00 a piece | 4 daysReady 26 Oct | 82% booked160 h a week | 94% on timeControlled Goods registered | WO-26-0712 |
| Shop QC-018Lévis, QCNot selected | $1,064.00$290.00 setup, $64.50 a piece | 5 daysReady 27 Oct | 60% booked110 h a week | 95% on timeControlled Goods registered |
Shop ON-007: 5-axis operations and CMM report only; parts arrive from the 3-axis shop.
The request as sent
What each shop got: the operations, the drawing and model, and the email.
Operations
| Op | Operation | Specification | Machine |
|---|---|---|---|
| 40 | Ports at compound angles, Ø22 H7 | 22.5° and 30° | 5-axis |
| 50 | Finish port faces and chamfers | ISO 2768-m | 5-axis |
| 60 | CMM inspection to report | Full report, 12 of 12 | Inspection |
Drawing and model
The shops download them from the request in their portal.
actuator-housing-rev-c.step
3.4 MB, STEP model, rev C
DB-0988-C.pdf
655 KB, drawing, rev C
Email to the shops
Sent 14 Oct 2026, 12:00 to 2 shops
Machining-only request MR-26-0426: Actuator housing, 12 pieces
Your price for operations 40, 50, 60 only. Metal arrives cut to size with its mill certificate on 16 Nov 2026. Parts due at your dock on 20 Nov 2026. Reply by 15 Oct 2026.
Split job: parts arrive from Shop NS-014 after operations 10 to 30, with datums marked.