Skip to content

Order CF-26-10371

Machining

Actuator housing, rev C, 12 pieces. Placed 20 Oct 2026, due in Kanata, ON on 24 Nov 2026. $3,977.43, paid by Pre-authorized debit.

  1. Metal (Done)

    Metal ordered from the mill

    PO-26-0839 · 22 Oct

  2. Carried (In progress)

    Metal at the first shop

    Dartmouth, NS

    SH-26-0781 · 4 Nov

  3. Machined (Not yet)

    Operations 40 to 60

    Cambridge, ON

    WO-26-0712 · Due 19 Nov

  4. Inspected (Not yet)

    CMM inspection

    Cambridge, ON

    Due 20 Nov

  5. Shipped (Not yet)

    Delivered

    Kanata, ON

    SH-26-0783 · Due 24 Nov

  6. Record (Not yet)

Canadian content recordCR-26-10371

In progress: each step signs as it happens; the record is issued at delivery.

3 of 9 steps signed
Country of meltUnited States7075-T651, melted 30 Aug 2026, heat 7B0932, from mill certificate MTC-26-0839. Aluminum counts as Canadian only if smelted and cast in Canada.
  1. 10Smelted and castUnited States, outside Canada (Outside Canada)MTC-26-0839, heat 7B0932
  2. 20Bought, cut to sizeOntarioBR-26-0839, 12 of 12 pieces
  3. 30Carried to the shopOntario to Dartmouth, NSWaybill 7741 2302 47
  4. 40MachinedDartmouth, NSShop NS-014, ops 10 to 30Signs when it happens
  5. 45Carried to the next shopDartmouth, NS to Cambridge, ONWaybill SH-26-0782Signs when it happens
  6. 50MachinedCambridge, ONShop ON-007, ops 40 to 60Signs when it happens
  7. 60InspectedCambridge, ONReport CMM, 12 of 12Signs when it happens
  8. 70ShippedCambridge, ON to Kanata, ONWaybill when bookedSigns when it happens
  9. 80Record issuedcanadafab.caCF-26-10371Signs when it happens

Shops and provinces: Canadian metal supplier, Ontario; Shop NS-014, Dartmouth, NS; Shop ON-007, Cambridge, ON. Carriers: Carrier A, 1 leg, Canadian. Demo record, demo data.

Actuator housing, rev C12 pieces · DB-0988 · 7075-T651$3,288.85

Documents

Each download is logged.

  • Drawing DB-0988 rev CDB-0988 · 14 Oct 2026In the product it downloads as a PDF, and each download is written to the audit log.PDF
  • Quote CF-Q-26-0930CF-Q-26-0930 · 15 Oct 2026PDF
  • Order confirmation CF-26-10371CF-26-10371 · 20 Oct 2026PDF
  • Mill certificate MTC-26-0839MTC-26-0839 · 3 Nov 2026PDF