JOB-26-0419
ShippingOn trackExpediteDrive shaft, rev B, for Demo buyer company, at Shop QC-011.
- Buyer
- Demo buyer company
- Kanata, ON
- Ships by
- 4 Nov 2026
- Delivery by 6 Nov 2026
- Owner
- Jordan (demo)
- Operations, freight and suppliers
Cost sheet
Study defaults, not approved yet- Quote, before tax
- $1,421.11
- What the buyer sees
- Our cost
- $888.72
- Supplier, shop and carriers
- Gross margin
- 37.5%
- $532.39
- Bids against check price
- 98.6%
- 100% means the bid matches the rules
Metal: Drive shaft
4140, 20 pieces, Turned. Priced from the dated table, cheapest supplier first.
Stock from the geometry
- Part envelope
- 180 × 25 × 25 mm
- Turned
- Allowance
- 1 mm on the radius, 1 mm each face
- Needed
- Ø27 × 182 mm
- Stock size
- Round bar, Ø1.125 × 7.250 in
- 28.58 × 28.58 × 184.15 mm
- Blanks
- 20, no spares
- Weight
- 18.5 kg
- 0.9 kg a blank
Lengths round up to the saw increment, 0.125 in, on the supplier’s size list.
Price from the table
Canadian metal supplier, QC. Price list valid 1 Oct 2026 to 31 Dec 2026.
| Supplier | Price | Cost | Line |
|---|---|---|---|
| Canadian metal supplier, QCCheapest, on the quote | $6.50 a kg | $160.52 | $192.62 |
| Canadian metal supplier, ON | $3.05 a lb ($6.72 a kg) | $210.00 | $252.00 |
Machining
Machining-only bids from shops, with the metal supplied cut to size. The line adds a 28% gross margin.
- Bid, machining only
- $672.00
- Rules check price
- $681.40
- Bid against check
- 98.6%
- Machining line
- $1,166.67
Line = bid ÷ (1 − 28%) × lead factor 1.25.
MR-26-0431Operations 10 to 40, 20 pieces
| Shop | Price | Days | Ships | Against check | Status |
|---|---|---|---|---|---|
| Shop QC-011Saint-Laurent, QC | $672.00 | 4 days | 6 Nov | 98.6% | On the quote |
| Shop ON-012Windsor, ON | $718.00 | 5 days | 7 Nov | 105.4% | Not selected |
Freight
Every leg from the carrier-neutral rating layer, Canada-only on. The line adds a 10% handling markup.
Margins and overrides
The margins this quote went out with.
Override history
Every change to the model on this job: the variable, the model’s value and the new one, the reason code and who made it.
No overrides on this job. It’s priced as the model has it.